The estimated cost of the project is in the region of Rs.12.5 Crores.
M/s. Paranjpe and Deshpande, as Hon. Consulting Architects have designed the school building and M/s. Phulkar & Kangutkar are overseeing the construction as our chartered architects. M/s. Kankon Managements are the Project Management Consultants and Shri. Harshad Gokani is helping the institution as the Structural Engineer.
A brief look at the comparative statement below will be helpful to understand the infrastructural enhancements planned.
Total Area under use | Current | Future |
Classrooms | 28 (500 Sq.ft. each) | 40 (600 Sq.ft. each) |
Laboratories | 1 (1000 Sq.ft) | 3 (1300 Sq.ft. each) |
Computer Room | 1 (500 Sq.ft) | 1 (1300 Sq.ft) |
Workshop | – | 1 (1300 Sq.ft.) |
Library | 1000 (1000 Sq.ft.) | 1 (2550 Sq.ft.) |
Atrium | – | 1 (850 Sq.ft.) |
Drawing Studio | – | 1 (1300 Sq.ft.) |
Store room | 2 (100 Sq.ft each) | 1 (1300 Sq,ft) |
Lifts | – | 3 |
Staircases | 1 | 2 |
24 classrooms have been in use since June-2010. Another 12 classrooms will be available from June-2011. This will complete Phase 1 of the project.